Projects and service area.
Remote O&M, remediation, commissioning support and site inspections on utility-scale solar sites in southern Alberta, dispatched from Calgary.
- Multi-GWOngoing remote O&M portfolio of tracker sites
- 100 MWCentre saddle bracket remediation by Hemora-employed crews
- 5 sitesOperating utility-scale sites supported in southern Alberta
- Since 2021Construction and O&M support on utility-scale tracker sites
Work to date
Site names stay off this website until each owner agrees to be listed. References are available on request.
- Tracker remote O&M
- A multi-gigawatt portfolio, ongoing. Alarm triage, remote troubleshooting, dispatch and performance reporting for GameChange Solar tracker sites, including five utility-scale sites in Alberta.
- Centre saddle bracket remediation
- 100 MW. Hemora-employed field crew working tracker by tracker to the manufacturer’s procedure.
- Commissioning support
- Five projects. Field presence for tracker commissioning across those five Alberta sites: walkdowns, punch lists and functional checks.
- Construction quality
- Site inspections during the build. Quality control of tracker systems on large grid-connected sites, with field reports for each visit.
- Since 2021
- Founded to support construction and O&M on the first GameChange Solar tracker systems built in Canada.
Service area
The five sites we support today are all within about 210 km of Calgary, a few hours by road. Most of southern Alberta’s operating solar and BESS fleet sits inside the same rings.
- Five sites Hemora supports today
- Hemora base, Calgary
- Other operating solar sites (context)
- Other sites with battery storage (context)
Locations and rings are approximate, and distances are straight-line. Muted markers show southern Alberta’s broader operating fleet for regional context only; Hemora has not worked on those sites.
See a closeout package
An anonymized extract of real field records from a damper arm inspection and re-spacing job on 921 trackers, in the format delivered at closeout. Read it here or download the PDF.
units closed, all four steps signed off
found below minimum gap, all corrected
exceptions logged, 1 worked unit left open
before and after photos on file
Of the 98 units measured, 75 had a damper arm below the required minimum gap as found. All 98 were left at the specified spacing, torqued and torque-marked. One unit was left open because its existing fastener was stripped, and stays open until the fix is approved.
| Field day | Started | Closed | Open | Notes |
|---|---|---|---|---|
| Day 1 | 46 | 46 | 0 | No exceptions |
| Day 2 | 23 | 23 | 0 | No exceptions |
| Day 3 | 30 | 29 | 1 | Three stripped fasteners found and logged |
| Extract total | 99 | 98 | 1 | 822 units in scope not yet started |
Every check in the four-step procedure is logged individually against the tracker. As-found checks record the condition found before work, not the condition left.
| Step | Check | Units | Pass | Fail |
|---|---|---|---|---|
| 1. Initial inspection | Damper arm located and spacing checked against chartAs-found check: records initial condition before repositioning. | 99 | 76 | 23 |
| 1. Initial inspection | Existing self-drilling screw removed from damper armOne screw stripped inside torque tube; logged as open exception. | 99 | 98 | 1 |
| 2. Spacing measurement | Calculated spacing meets minimum gap from temperature chartAs-found check. Required minimum gap: 1.00 in on all 98 units. | 98 | 23 | 75 |
| 2. Spacing measurement | Damper arm at specified spacing after repositioning | 98 | 98 | 0 |
| 3. Final fastening | All clamp hardware torqued within range, torque-marked & reference scribed | 98 | 98 | 0 |
| 4. Completion QC | Used material, packaging and removed hardware taken off site | 98 | 98 | 0 |
Why exceptions stay open: A crew never signs off a unit it could not finish to the manufacturer’s procedure. An exception stays open until you approve the fix.
| Unit | Exception found | Action taken | Status |
|---|---|---|---|
| R08-T082 | Day 3. Existing self-drilling screw stripped inside the torque tube during removal. | Work stopped at step 1. Unit not signed off. | Open |
| Not yet started (×2) | Day 3. Stripped self-drilling screws spotted on two additional trackers in scope. | Logged against each tracker before work reaches it. | Open |
| Sample closed unit: R13-T065 | Field record | Result |
|---|---|---|
| 1. Initial inspection | Day 1, 11:14. Four checks completed. | 4 of 4 pass |
| 2. Spacing measurement | Damper outboard of post. Minimum gap 1.00 in; below minimum as found. | Repositioned to spec |
| 3. Final fastening | Day 1, 11:14. Five checks, including torque and torque marks. | 5 of 5 pass |
| 4. Completion QC | Day 1, 11:14. Site left clean. | Closed |
Captured in field software built by our own development team. Records publish from the field the same day, with or without cellular signal, and come with a spreadsheet and full photo export.
| What a full closeout package includes | Detail |
|---|---|
| Unit map and per-unit spreadsheet | Every tracker in scope coloured by status, plus one row per unit and procedure step. |
| Before and after photos | Photos linked to unit IDs. This extract has 15 before and 16 after, with the measurement in frame, across 15 units. |
| Parts reconciliation | Parts issued, installed, returned and tagged for RMA. |
| Training and safety records | Lead signed off by client trainer, crew signed off by lead, plus crew-hours, stop-work events and safety observations. |
The PDF has six pages: summary, unit map, results by check, exceptions log and one full unit record. Site, owner, people and part numbers are removed. The counts are real.
- WCB Alberta 9306770, in good standing
- No lost-time incidents since field work began
- Insurance certificates issued before mobilizing
- SECOR in progress, audit planned for spring 2027
Have field work coming up?
Send the site, unit count, task and window. We’ll come back with a crew plan and a paid trial block: one block at an agreed rate, so the rest is quoted from measured pace.